Public Meeting #3
The meeting held on July 12, 2017 at DePaul University Student Center was attended by 262 people. The meeting was an open house format with an introduction video, online survey, continuous PowerPoint presentation, and exhibit boards for review. Comments will be accepted through the entire project development process. However, to become part of the public record of this Public Meeting, comments must be received or postmarked by August 9, 2017.
Online Survey Results
All of the questions and comments have been collected and compiled to provide a comprehensive review of the topics raised along with project team’s responses.
Meeting Materials
PRESENTATION
EXHIBITS
Level 1 Screening Summary
- Level 1 Screening Summary
- Initial Range of Alternatives
- 2040 No-Action Alternative
- Transitways Alternatives
- Managed Lanes Alternatives
- Tunnels and Causeways Alternatives
- Context Tailored Treatments Alternatives
- Context Tailored Treatments Alternatives (continued)
Context Tailored Treatments – Grand Avenue to Diversey Parkway
- Grand Avenue to Diversey Parkway – Alternative 1
- Grand Avenue to Diversey Parkway – Alternative 2 and 3
- Compressed Junction with Retaining Wall Rendering
- Chicago Avenue Rendering
- Oak Street – Option 1 Rendering
- Oak Street – Option 2 Rendering
- North Avenue Rendering
- Fullerton Avenue Rendering
- Typical Sections – Grand Avenue to Irving Park Road
Context Tailored Treatments – Diversey Parkway to Montrose Avenue
- Diversey Parkway to Montrose Avenue – Alternative 1
- Diversey Parkway to Montrose Avenue – Alternative 1 with Addison Street Junction
- Diversey Parkway to Montrose Avenue – Alternative 2 and 3
- Addison Street Rendering
- Belmont Harbor Rendering
Context Tailored Treatments – Montrose Avenue to Hollywood Avenue
- Montrose Avenue to Hollywood Avenue – Alternative 1
- Montrose Avenue to Hollywood Avenue – Alternative 2 and 3
- Montrose Avenue Rendering
- Typical Sections – Montrose Avenue to Hollywood Avenue
Shoreline Protection